Mudassir Iqbal

Project Schedule Management

Project Schedule Management Processes
To Project Schedule Management Blog

The expectation in Project Schedule management processes from the project manager is to give the dates when the stakeholders can expect the deliverables. It is said that if you don’t plan, you are actually planning to fail. The majority of the processes here i.e 5 out of 6 focuses on developing a viable and actionable project schedule. As a project manager, you would be discussing the missed deadlines in addition to scope creep and risk mitigation plan in every progress meeting. Control Project schedule helps the project manager to remain pro-active and influence factors of changes.

 

 

Project Schedule Management Processes

Plan Schedule Management (Planning)

Inputs Tools and Techniques Outputs
  • Project charter
  • Project management plan
    • Scope management plan
    • Development approach
  • Enterprise environmental factors
  • Organizational process assets
  • Expert judgment
  • Data analysis
  • Meetings
  • Schedule management plan

 

Define Activities (Planning)

Inputs Tools and Techniques Outputs
  • Project management plan
    • Schedule management plan
    • Scope baseline
  • Enterprise environmental factors
  • Organizational process assets
  • Expert judgment
  • Decomposition
  • Rolling wave planning
  • Meetings
  • ctivity list
  • Activity attributes
  • Milestone list
  • Change requests
  • Project management plan updates
    • Schedule baseline
    • Cost baseline

 

Sequence Activities (Planning)

Inputs Tools and Techniques Outputs
  • Project management plan
    • Schedule management plan
    • Scope baseline
  • Project documents
    • Activity attributes
    • Activity list
    • Assumption log
    • Milestone list
  • Enterprise environmental factors
  • Organizational process assets
  • Precedence diagramming method
  • Dependency determination and integration
  • Leads and lags
  • Project management information system
  • Prject schedule network diagrams
  • Project documents updates
    • Activity attributes
    • Activity list
    • Assumption log
    • Milestone list

 

Estimate Activity Duration (Planning)

Inputs Tools and Techniques Outputs
  • Project management plan
    • Schedule management plan
    • Scope baseline
  • Project documents
    • Activity attributes
    • Activity list
    • Assumption log
    • Lessons learned register
    • Milestone list
    • Project team assignments
    • RBS – Resource breakdown structure
    • Resource calendars
    • Resource requirements
    • Risk register
  • Enterprise environmental factors
  • Organizational process assets
  • Expert judgment
  • Analogous estimating
  • Parametric estimating
  • Three-point estimating
  • Bottom-up estimating
  • Data analysis
    • Alternatives analysis
    • Reserve analysis
  • Decision making
  • Meetings
  • Duration estimates
  • Basis of estimates
  • Project documents updates
    • Activity attributes
    • Assumption log
    • Lessons learned register

 

Develop Schedule  (Planning)

Inputs Tools and Techniques Outputs
  • Project management plan
    • Schedule management plan
    • Scope baseline
  • Project documents
    • Activity attributes
    • Activity list
    • Assumption log
    • Basis of estimates
    • Duration estimates
    • Lessons learned register
    • Milestone list
    • Project schedule network diagrams
    • Project team assignments
    • Resource calendars
    • Resource requirements
    • Risk register
  • Agreements
  • Enterprise environmental factors
  • Organizational process assets
  • Schedule network analysis
  • Critical path method
  • Resource optimization
  • Data analysis
    • What-if scenario analysis
    • Simulation
  • Leads and lags
  • Schedule compression
  • Project management information system
  • Agile release planning
  • Schedule baseline
  • Project schedule
  • Schedule data
  • Project calendars
  • Change requests
  • Project management plan updates
    • Schedule management plan
    • Cost baseline
  • Project documents updates
    • Activity attributes
    • Assumption log
    • Duration estimates
    • Lessons learned register
    • Resource requirements
    • Risk register

 

Control Schedule (Monitoring and Controlling)

Inputs Tools and Techniques Outputs
  • Project management plan
    • Schedule management plan
    • Schedule baseline
    • Scope baseline
    • Performance measurement baseline
  • Project documents
    • Lessons learned register
    • Project calendars
    • Project schedule
    • Resource calendars
    • Schedule data
  • Work performance data
  • Organizational process assets
  • Data analysis
    • Earned value analysis
    • Iteration burndown chart
    • Performance reviews
    • Trend analysis
    • Variance analysis
    • What-if scenario analysis
  • Critical path method
  • Project management information system
  • Resource optimization
  • Leads and lags
  • Schedule compression
  • Work performance information
  • Schedule forecasts
  • Change requests
  • Project management plan updates
    • Schedule management plan
    • Schedule baseline
    • Cost baseline
    • Performance measurement baseline
  • Project documents updates
    • Assumption log
    • Basis of estimates
    • Lessons learned register
    • Project schedule
    • Resource calendars
    • Risk register
    • Schedule data

[pt_view id=”c356c37lza”]

Leave a Reply

Book Your PMP Training and Earn Your PMP Certification Today!