Project Cost Management Video – PMP/CAPM

Project Cost Management

Project Cost Management Processes
To Project Cost Management Blog

No Initiative will be approved and no project will get into execution until the Project Manager or Project Management team provides the project schedule and the project budget.  These are baselined during the Planning process Group so that can be used for measuring the progress of the project against a Project Management Plan and determine if the project is on track or if it requires an adjustment either through corrective actions, preventive actions, Defect repair or change requests.  Project Cost Management Management processes provide the required ability to the Project Manager, so that s/he can keep the project within budget and deliver the project objectives successfully.

Project Cost Management Processes

Plan Cost Management (Planning)

Inputs Tools and Techniques Outputs
  • Project charter
  • Project management plan
    • Schedule management plan
    • Risk management plan
  • Enterprise environmental factors
  • Organizational process assets
  • Expert judgment
  • Data analysis
  • Meetings
  • Cost management plan

Estimate Costs (Planning)

Inputs Tools and Techniques Outputs
  • Project management plan
    • Cost management plan
    • Quality management plan
    • Scope baseline
  • Project documents
    • Lessons learned register
    • Project schedule
    • Resources requirements
    • Risk register
  • Enterprise environmental factors
  • Organizational process assets
  • Expert judgment
  • Analogous estimating
  • Parametric estimating
  • Bottom-up estimating
  • Three-point estimating
  • Data analysis
    • Alternatives analysis
    • Reserve analysis
    • Cost of quality
  • Project management information system
  • Decision making
    • Voting
  • Cost estimates
  • Basis of estimates
  • Project documents updates
    • Assumption log
    • Lessons learned register
    • Risk register

Determine Budget (Planning)

Inputs Tools and Techniques Outputs
  • Project management plan
    • Cost management plan
    • Resource management plan
    • Scope baseline
  • Project documents
    • Basis of estimates
    • Cost estimates
    • Project schedule
    • Risk register
  • Business documents
    • Business case
    • Benefits management plan
  • Agreements
  • Enterprise environmental factors
  • Organizational process assets
  • Expert judgment
  • Cost aggregation
  • Data analysis
    • Reserve analysis
  • Historical information review
  • Funding limit reconciliation
  • Financing
  • Cost baseline
  • Project funding requirements
  • Project documents updates
    • Cost estimates
    • Project schedule
    • Risk register

Control Costs (Monitoring and Controlling)

Inputs Tools and Techniques Outputs
  • Project management plan
    • Cost management plan
    • Cost baseline
    • Performance measurement baseline
  • Project documents
    • Lessons learned register
  • Project funding requirements
  • Work performance data
  • Organizational process assets
  • Expert judgment
  • Data analysis
    • Earned value analysis
    • Variance analysis
    • Trend analysis
    • Reserve analysis
  • To-complete performance index
  • Project management information system
  • Work performance information
  • Cost forecasts
  • Change requests
  • Project management plan updates
    • Cost management plan
    • Cost baseline
    • Performance measurement baseline
  • Project documents updates
    • Assumption log
    • Basis of estimates
    • Cost estimates
    • Lessons learned register
    • Risk register

Don’t forget to join and subscribe,


Mudassir Iqbal, PMPMudassir Iqbal, PMPMudassir Iqbal, PMPMudassir Iqbal, PMPMudassir Iqbal, PMPMudassir Iqbal, PMP

The #𝗣𝗠𝗣𝟯𝟬𝗗𝗮𝘆𝘀𝗖𝗵𝗮𝗹𝗹𝗲𝗻𝗴𝗲 is designed to efficiently teach you everything you need to know and to prepare you for the PMP examination 𝓲𝓷 𝓪 𝓶𝓮𝓻𝓮 𝟑𝟎 𝓭𝓪𝔂𝓼, using the 𝙗𝙞𝙩𝙚-𝙨𝙞𝙯𝙚𝙙 𝙞𝙣𝙛𝙤𝙧𝙢𝙖𝙩𝙞𝙤𝙣 method. Allow me to help you to achieve PMP Certification!

Leave a Reply

%d bloggers like this: